job duration
RH

Forum home » Delegate support and help forum » Microsoft Project Training and help » Job duration

Job duration

resolvedResolved · Urgent Priority · Version 2010

Kerry has attended:
Project Introduction course
Project Intermediate course

Job duration

hi,

i have put in set amount of days for a particular task but is comes up with 74.64 days, how do i resolve this?

could i send the document to you to have a look please?

Many thanks,

RE: job duration

Hi Kerry

Yes please send your Project file so I can answer you query more easily. After posting click on the Upload button to attach your file.

Regards

Doug

Doug Dunn
Best STL

Edited on Mon 21 Jan 2013, 16:27

RE: job duration

Hi Doug,

thanks, will do

where is the upload button?

thanks,

RE: job duration

Hi Kerry,

Sorry for slow response. I'm not training today so will be able to look at your query.

To send an attachment click on Submit and afterwards there should be an Upload button.

If not then send to Doug@stl-training.co.uk

Regards
Doug Dunn
Best STL

RE: job duration

Hi Kerry

Thank you for sending through your project. It looks to me like the cause of the problem you are encountering is a conflict between two calendar settings.

First take a look at Change Working Time. If you click on a regular day in your calendar it shows (to the right of the calendar) that there are two parts to the day 8:00 to 12:00 and 13:00 to 16:00 which gives room for a total of 7 hours of work in the day.

If you now click on the Options button at the bottom of the dialogue box and take a look at the section labelled Hours per day. Usually the figure here matches the space we set for hours of work in the calendar (in this case 7).

One cause of fractional durations can be if tasks are first created using the standard 8 hours per day setting in the calendar (8:00 to 12:00 and 13:00 to 17:00) and then later the calendar time for the end of the day is set earlier (or later). With a shorter calendar, as we have here, Project has to somehow show the extra hours that previously fitted the longer day. This is when the display shows "excess" duration spilling over and creating fractions.

Before you make any further changes make a backup of your plan. If you have a version that doesn't have fractions in it. You may wish to roll back to that version.

Fixing this problem can be tricky. Changing the settings in the dialogue boxes will affect new tasks. You may need to copy your tasks into a new Project where the settings are correctly aligned, then set your durations and finally re-assign your resources.

With a Project of this size try a test with a few tasks first.
Let me know how you get on or if you have further questions.

Kind regards,
Andrew

Thu 31 Jan 2013: Automatically marked as resolved.


 

MS Project tip:

Create own ribbon tab - Project 2010

a. In Project click on the File tab
b. Select Options from left hand side
c. Choose the Customize Ribbon section
d. Click the New Tab button (below the list of tabs on the right hand side of the dialog box)
e. Select the New Tab (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
f. Select the New Group (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
g. Add commands to your tab and group by locating them on the list on the right hand side (remembering that you can change the list using the drop down box at the top of the list of commands) and clicking the Add button between the two panes to add them to your tab and group
h. You can rearrange the commands in your group, the groups on any tab or the tabs, using the up and down arrow buttons beside the list of tabs.
i. Click OK to apply your changes

View all MS Project hints and tips


Server loaded in 0.06 secs.