microsoft project
RH

Forum home » Delegate support and help forum » Microsoft Project Training and help » Microsoft Project

Microsoft Project

resolvedResolved · Low Priority · Version 2007

Neil has attended:
Project Introduction course
Project Intermediate course

Microsoft Project

How do I build in Project Team holidays & other commitments to my resource planning?

RE: Microsoft Project

Hi Neil

Thank you for your question.
You can incorporate resource non-availability caused by things like holidays and other commitments by adjusting the working time calendars for the resources in question.

To do this switch to Resource sheet view then double click on the name of the resource in question.
From the dialogue box that opens click on the Change Working time button (it's on the general tab). From here you can create exceptions as needed to the resource's calendar. You can also adjust the underlying default work week pattern in the Work weeks tab.

I hope this helps - do let me know if you have any further questions.

Kind regards,
Andrew

Mon 18 Jun 2012: Automatically marked as resolved.


 

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)

View all MS Project hints and tips


Server loaded in 0.05 secs.