Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

ms project training - milestone

Forum home » Delegate support and help forum » Microsoft Project Training and help » ms project training - Milestone

ms project training - Milestone

ResolvedVersion Standard

Peter has attended:
Project Intermediate course
Project Introduction course

Milestone

How do i create a milestone?

Edited on Tue 20 Mar 2007, 14:23

RE: Milestone

Hi Peter

A milestone is used to indicate a particular point in your project's life. To create a miletone in Project just add a task an set its duration to zero. Project redraws the the task on the Gantt chart as a black diamond plus its start date.

Milestones are useful to clearly indicate key dates in your project.

Hope this is helpful - contact us again if you have any further questions.

Thanks
Andrew

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.

View all MS Project hints and tips