Why does the Budget cost report give different values depending on whether the summary tasks are collapsed or expanded?

RE: Project

Hi Carole

Thank you for your question. By default the Budget report is set to exclude summary tasks. Go to View > Reports > Custom and select the Budget report from the list then click Edit. Put a tick in the box Show Summary Tasks and click OK.

Now when you report you will see values that match your table. Use the Show button on the formatting toolbar to quickly set how much detail you want to see in your report then run the Budget report as normal.

Let us know how you get on.

Kind regards,
Andrew

Mon 20 Jul 2009: Automatically marked as resolved.


 

MS Project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.

View all MS Project hints and tips


Server loaded in 0.05 secs.