project server training london - progress lines
RH

Forum home » Delegate support and help forum » Microsoft Project Training and help » project server training london - Progress Lines

project server training london - Progress Lines

resolvedResolved · Low Priority · Version Standard

Will has attended:
Project Intro Intermediate course

Progress Lines

How do I add a vertical line to the Gantt chart to indicate significant dates?

RE: Progress Lines

right click and select Gridlines and select bottom tier column and select the line type


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Server loaded in 0.05 secs.