Stewart has attended:
No courses
Standard MS Project Formulas
Is there any way of getting hold of the existing formulas in the default cells in MS Project?
I want to create a customised formula which for a a new column:
Start1 = "Finish1" Date of "Predecessor" + 1 day or "Project start date" if "Predecessor" is 0/valueless
Essentially this is the same as the default formula for column "Start" with reference to "Finish1" instead of "Finish".
So if i had access to the default column formulas im sure i could work out new formulas for my new columns.
Alternatively if these are not available, does anyone have a good list of basic formulas for MS Project or can anyone help with my specific query above.
Many thanks for your time.
RE: Standard MS Project Formulas
Hi Stewart
Thank you for your question. Here is a Microsoft article describing the syntax of formulas in custom fields.
https://support.office.microsoft.com/en-gb/article/Project-functions-for-custom-fields-7e525143-380f-4083-8d5a-3ecc6ba44f22?CorrelationId=2811c550-4774-4de8-8cc2-4e7eb15269a7& ;ui=en-US&rs=en-GB&ad=GB
I hope you find this helpful - let us know if you have any further questions.
Kind regards,
Andrew