Danielle has attended:
Project Intermediate course
% Complete column
Hi,
How do I set the "% Complete" column to update either : 1/ automatically (assumed completed works based on the duration)
2/ manually (where estimated completion of work achieved)
Thank you.
RE: % Complete column
Hi Danielle
thank you for your question - the "% Complete" column can be updated in a number of ways.
You can manually type in the % and Project will draw a progress line though the bar on the cart
On the Task tab you can also use the 0% 25% 50% 75% and 100% buttons to record progress.
A different approach that might address your first point is to click the Mark on Track button. This will record progress on the task or tasks selected up to today's date.
I hope this helps - let me know if you have any further questions.
Kind regards,
Andrew