Forum home » Delegate support and help forum » Microsoft Project Training and help » Columns on gantt chart

Columns on gantt chart

ResolvedVersion 2007

Karen has attended:
Project Introduction course

Columns on gantt chart

can a 'week' column in the gantt chart be highlighted, eg to show a school half term, but continue as working time

RE: Columns on gantt chart

Hi Karen

I don't think there's a way of highlighting working time such as half term. One way though would be to use the Drawing tools and draw a coloured rectangle representing the period. Drawing object can be sent behind the task bars by right click, Arrange.

This is not a good solution if you zoom to a different timescale though.

Doug Dunn
Best STL

RE: Columns on gantt chart

Thanks for the suggestion. I'm putting my new found skills to the test this morning by setting up my own programme so I'll give it a go but appreciate the limitations!

RE: Columns on gantt chart

Great to put your skills into action.
Good luck Karen!

Fri 4 Oct 2013: Automatically marked as resolved.

MS Project tip:

Enter a Date

You can enter today's date (or tomorrow's date) in a date field, by simply typing in the word 'today'or 'tomorrow' and Project will insert the date for you.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.12 secs.