Linda has attended:
Project Intro Intermediate course
Microsoft Project
In training recently for example we set up resources for say 1 Project Manager with Max. Units at 100% and 2 Project Assistants as a single resource but with Max. Units set to 200%.
Working in the Gantt chart view with the window split. When assigning these resources to a task with 'EFFORT DRIVEN' ticked, the task duration halves when both Project Manager and Project Assistant resources are assigned but, when I change the Units on the Project Assistants resource to 200% this does not further reduce the task duration. If there is effectively 1 project manager and 2 project assistants (not one) assigned to the task, why is the task duration not decreased by 2 thirds say?
RE: Microsoft Project
Hi Linda
Good question!
Project doesn't recalculate the duration when there are a mixture of resources and you increase the % Units of one of them. As in your example a Project Manager and a Project Assistant and you increase from 100% to 200% for the Project Assistant.
The way round is to remove the Project Assistant in the Details pane. Then after pressing Ok assign the Project Assistant again this time as 200%.
The task duration then recalculates to be a third of the original duration.
Hope that helps Linda.
Regards
Doug Dunn
Best STL