How do you include newly added tasks to the baseline, whilst not resetting the baseline for the overall project?

RE: Baselining

Hi Alex, thanks for your query. Look for "Update a baseline or an interim plan" here:

http://office.microsoft.com/en-us/project-help/create-or-update-a-baseline-or-an-interim-plan-HA010156784.aspx #BM4

Hope this helps,

Anthony

MS Project tip:

Set default task type - Project 2010

a. In Project, click on the File tab
b. Select Options from left hand side
c. Click on Schedule to set the scheduling options
d. Set the Default Task type box to your chosen option
i. Generally if you plan/estimate your projects using durations you should use fixed duration, and untick the box New tasks are effort driven, if you plan/estimate with person hours use fixed work, or for plans estimated with the proportion of resources time use fixed units, and untick the box New tasks are effort driven)
e. Click OK to apply your changes