ResolvedVersion 2010

Naresh has attended:
Project Intro Intermediate course

Critical Path

Does MS Project automatically find or set the Critical Path in a plan (in Tracking Gantt view) or can I manually set it. If automatic then how does it do it?

RE: Critical Path

Hi Naresh,

Thank you for your question. MS Project calculates the Critical path for you and it shows the critical tasks in red. Also if you apply the Schedule table to the Gantt Chart, it will show you the Total and Free slack values.

It is a bit of a detailed process to explain in a response, so I have included a link to a site with a good explanation.

Basically, it uses the earliest and latest start and finish dates to work out the slack or float values. If the total slack is 0 then it is critical if above 0 non critical.

Please find the following link:

http://syque.com/quality_tools/tools/TOOLS16.htm

I hope this helps.

Regards

Simon

Thu 16 Feb 2012: Automatically marked as resolved.

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.18 secs.