microsoft project training seminar - milestone

Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft project training seminar - Milestone

microsoft project training seminar - Milestone

resolvedResolved · Low Priority · Version Standard

Olga has attended:
Project Introduction course
Project Introduction course

Milestone

How do I create the above? And what the results of creating it?
Thanks,
Olga

RE: Milestone

Olga,

Thanks for the question.

Enter a zero 0 day in the duration part of the task.

Rich


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Server loaded in 0.07 secs.