ms project

Forum home » Delegate support and help forum » Microsoft Project Training and help » MS Project

MS Project

resolvedResolved · Low Priority · Version 2003

Peter has attended:
Project Introduction course

MS Project

Can you automatically import UK bank holidays into a template so you don't have to do them manually?

RE: MS Project

Hi Peter

Thank you for your question. Unfortunately there is no automatic feature to do this. However if you if you do set up a plan to contain bank holidays you could save it as a template (File > Save as then change the type to template) and use this as the basis for new project documents.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Server loaded in 0.07 secs.