Where there are breaks in a task, is it possible to show milestones linked to the end of each break point in the task?

Thanks
Bassam

RE: breaks in a task

Hi Bassam

Have you marked the task as a milestone? Or used a zero day duration?

You might have to format the milestone task to show the entire duration instead of the end date

Kind regards
Wendy Canelas
Microsoft Office Trainer

RE: breaks in a task

Hi Wendy

Perhaps my question was not very clear. I have a task with multiple breaks and I wanted to show (on the next few lines of the Gantt chart) a number of milestones, each linked to one of the break point in the task.

I can achieve the same end result by breaking the task into a number of shorter tasks and linking each milestone to one of these shorter tasks but that would not be as neat.

Kind regards
Bassam

RE: breaks in a task

Hi Bassam

Unfortunately, I think you'll have to make them individual smaller tasks with milestones. You can't insert milestones between the breaks in a task.

Kind regards
Wendy Canelas
Microsoft Office Trainer

RE: breaks in a task

Noted. Thank you very much Wendy.
Regards
Bassam

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.11 secs.