Is there any way to associate deliverables (i.e. the expected results of a task or group of tasks) with the tasks? So that the Gantt chart (or some other view) shows both the task and the expected result from that task?
RE: deliverables
Hi Martin
Thanks for your question. Two options spring to mind. You could add a text field (eg text1) and use it to store deliverable information. You could then modify your bar styles (Format > Bar Styles) so that the field text1 is displayed beside each bar.
Alternatively you could make each of your deliverables a Summary task (by indenting the tasks below it) and the sub tasks represent progress towards achieving the desired outcome.
Hope this helps - do let us know if you have any questions.