Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

fixed duration effort offspecify

Forum home » Delegate support and help forum » Microsoft Project Training and help » Fixed duration effort off-specifying desired task timescale

Fixed duration effort off-specifying desired task timescale

ResolvedVersion 2007

Fixed duration effort off-specifying desired task timescale

My task is fixed duration, effort off but I can’t enter the start and finish dates of this task in this mode, it reverts back to 1 day duration so I have to change the mode, input the information and the change the mode back. Will I have to do this for every task?

All of my tasks are fixed duration effort off. I have a resource who can spend 30% of January working on this task. I want to put in the start and finish dates of this task so I can see the resource on the gannt view with his task showing for the duration of January reflecting the accurate amount of time he will be working throughout the month so it’s not just showing as 1 day duration.

I hoped to put in fixed duration effort off, input the start and end date of this task and put him at 30% but in fixed duration effort off mode, I can’t, the start and finish dates jump to show one day duration so I have to put the task onto another mode, fixed units to specify the dates I want, then add the resource then put the mode back to fixed duration effort off and then input the 30% for January.
Am I doing something wrong or is there an easier way to do this?

Many thanks!

RE: fixed duration effort off-specifying desired task timescale

Hi Emma

Thank you for your question. One thing you could try is to make the task, set it to the dates and assign the resource 100%. Once the assignment is made go back and reduce the units of resource to 30%. Your fixed duration setting should keep the task duration whilst reducing the amount of work involved.

Let me know if this gives you the answer you are looking for.

Kind regards,
Andrew

Tue 4 Dec 2012: Automatically marked as resolved.

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.