Hi Liz
Thanks for your question. The fastest way to link two tasks is to click on the bar of your first task in the Gantt chart and drag to the bar of the task that will be your successor. Once you let go you'll get a link drawn between your tasks, Finish to Start.
You can also block select multiple tasks and click on the link icons task. You can also double click on the successor task and from the predecessors tab choose the task you want to link to.
Hope this helps - do let us know if you have any further questions.
Kind regards,