ResolvedVersion 2010

Joanna has attended:
Excel Advanced course
Project Management - Framework & Processes course

Project 2010

How do I add a team rather than individuals to the resoucing?

RE: Project 2010

Hello Joanna,

When adding resources as a team as opposed to individuals, simply go to the Resource Sheet and enter the name you have chosen into the Resource Name column. In the Max. Units column you would normally enter a percentage / value for the number of members in the team. 500% would represent 5 team members.

When you assign the team to a task you must specify the percentage you are allocating to the task. I usually use the Assign Resources dialogue box for this. Select the Resource then enter the percentage into the Units column and press enter or click Assign. If the percentage is higher than the Max. Units % entered in the Resource sheet, then you will get a resource overallocation warning in the Indicators column.

For example, you have a task that requires only 4 of the 5 team members in Team A resource. Select the task and enter 400% into the Units column and press enter. Please be aware, that if you later edit the % to say 500% this will reduce the duration of the task EVEN IF THE TASK IS NOT EFFORT DRIVEN. If you do not want to reduce the duration first set the Task Type to Fixed Duration then increase the % value in the Units column.



I hope this resolves your question. If it has, please mark this question as resolved.

If you require further assistance, please reply to this post. Or perhaps you have another Microsoft Office question?

Have a great day.
Regards,

Rodney
Microsoft Office Specialist Trainer

Tue 7 Feb 2012: Automatically marked as resolved.

 

Training courses

Training information:

Welcome. Please choose your application (eg. Excel) and then post your question.

Our Microsoft Qualified trainers will then respond within 24 hours (working days).

Frequently Asked Questions
What does 'Resolved' mean?

Any suggestions, questions or comments? Please post in the Improve the forum thread.

Management Training tip:

Task List or To Do List

Don't confuse yourself with too many tasks on a to do list. The Task List is all the things that require attention, whether by you or others, now or later. The To Do list is your immediate daily plan, and is a subset of your Task List.

Keep your To Do list to no more than 5 major items.

View all Management Training hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.08 secs.