tasks

ResolvedVersion 2003

Gareth has attended:
Project Introduction course

Tasks

What is priority

RE: Tasks

Hi Gareth,

Thank you for your question.

When you create a task, in the task information box you can set a priority level of between 1 and 1000.

When you assign resources to a task, sometimes you will assign a resource to two jobs on the same day. Project will mark that resource as overallocated.

If Resource Levelling is used to resolve the overallocation, the lower the number, the more likely the task will be delayed to resolve the problem.

I hope this answers your question.

Regards

Simon

Wed 10 Jun 2009: Automatically marked as resolved.

MS Project tip:

Set default task type - Project 2010

a. In Project, click on the File tab
b. Select Options from left hand side
c. Click on Schedule to set the scheduling options
d. Set the Default Task type box to your chosen option
i. Generally if you plan/estimate your projects using durations you should use fixed duration, and untick the box New tasks are effort driven, if you plan/estimate with person hours use fixed work, or for plans estimated with the proportion of resources time use fixed units, and untick the box New tasks are effort driven)
e. Click OK to apply your changes