tracking

Forum home » Delegate support and help forum » Microsoft Project Training and help » Tracking

Tracking

resolvedResolved · High Priority · Version 2003

Patrick has attended:
Project Intro Intermediate course

Tracking

Is it possible to track multiple costs (as they happen) along the bar in the gantt Chart? So as you spend, it updates along the bar?

RE: Tracking

Hi Patrick

Thank you for your question

Could you clarify a few points for me please. By multiple costs do you mean different costs such as traveling expenses, Stationary etc.? Also do you want all the costs to appear on the bar, or just a total figure?

Thanks

Stephen

RE: Tracking

Hi Stephen,

Yes different costs, and as they are spent/inserted into the cost columns, they update along the bar in the gantt chart like a progress line, but instead of a progress line it is split up so it looks like a "rolled up bar".

Yes, I want to cost as they are spent shoing on the bar, and have the total figure at the far right of the bar.

I realise that you can insert figures, on, top, bottom, left and right of the bar.

Im sorry and I know this is complicated, but if you could help it would be sensational.

I want to know is it possible to do this?

Thanks

Pat

RE: Tracking

Hi Pat

Thank you for your question. The way progress is shown on the Gantt chart is controlled by the Format > Bar Styles dialog box.

You will see that the fields available to you in the From and To columns do not include cost fields. Without them I don't think it would be possible to show spend as a bar drawn through the task. Unfortunately limitations on the way the shapes are drawn mean there is no way that I can see to produce a multi-colour rolled up style progress bar within a task.

You may get more value by exporting your data into Excel and visualising it there. Choose File > Save As and set the output type to Excel Workbook and follow the Wizard.

I'm sorry we couldn't be of more help this time. Do let us know if you have any further questions.

Kind regards,
Andrew

RE: Tracking

Hello Pat

Have just been viewed your query
Am I correct in assuming you just need Prorated figures of Costs incurred throughout the project timespan?

If so, by updating the '% Completed' at regular 'Status Date' Intervals, you should find using the 'View' toolbar drop down Menu useful.
Clicking on 'Table:Entry' will then show you a series of options Project is able to Illustrate to you.
If you click on 'Cost', the Gantt view will change to show you Actual and Prorated Costs and Variances from your Project's Baseline Start.
This information is availible by using Microsoft's Step by Step Manual, Section 18- Measuring Performance with Earned Value Analysis.
It's not what I would call bedtime reading, but its a very useful tool for a complex programme like Project.
Hope it points you in the right direction -
Good Luck

David

RE: Tracking

Hi David - thank you for your suggestions too.

Kind regards,
Andrew

Tue 2 Jun 2009: Automatically marked as resolved.


 

MS Project tip:

Using the Quick Access Toolbar in Project 2010

The Quick Access Toolbar is included in virtually every Office product, including Project 2010 as well as Outlook 2010, Word 2010, Excel 2010, and PowerPoint 2010.

You will find the Quick Access Toolbar in the top-left side of the window. To begin, click the Customize button (it's the little black arrow at the end of the toolbar).

Simply click the commands you want to include.

Virtually any command can be added to the Quick Access Toolbar. Click the More Commands option and a new window will open from where you can browse the commands including those not on the ribbon.

View all MS Project hints and tips


Server loaded in 0.07 secs.