microsoft+project+course+london - milestones

Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft+project+course+london - Milestones

microsoft+project+course+london - Milestones

resolvedResolved · Low Priority · Version Standard

Lyndy has attended:
Project Intro Intermediate course
Project Intro Intermediate course

Milestones

how do I highlight milestones

RE: milestones

Go to format then bar styles and select milestone from here to change the bar colour for all milestones


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Server loaded in 0.09 secs.