ms project server consultancy - Hanging Depedency

ResolvedVersion Standard

Steve has attended:
Project Intro Intermediate course

Hanging Depedency

How do you identify hanging depedency

RE: Hanging Depedency

Hi Steve,

Simply add the successors column to the GANTT chart. To do this click right click on a column head and select insert column and choose successors.

Then activate the autofilter and choose NA. If NA doesn't appear, there will be a blank row in the drop down and you should select this.

Any items that then appear in the filtered that are not outline tasks, or the final milestone will need to be linked to the final milestone on a Finish to start basis.

Regards

Stephen

MS Project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.