ms project server consultancy - hanging depedency

Forum home » Delegate support and help forum » Microsoft Project Training and help » ms project server consultancy - Hanging Depedency

ms project server consultancy - Hanging Depedency

resolvedResolved · Low Priority · Version Standard

Steve has attended:
Project Intro Intermediate course

Hanging Depedency

How do you identify hanging depedency

RE: Hanging Depedency

Hi Steve,

Simply add the successors column to the GANTT chart. To do this click right click on a column head and select insert column and choose successors.

Then activate the autofilter and choose NA. If NA doesn't appear, there will be a blank row in the drop down and you should select this.

Any items that then appear in the filtered that are not outline tasks, or the final milestone will need to be linked to the final milestone on a Finish to start basis.

Regards

Stephen


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Server loaded in 0.07 secs.