project server courses - microsoft project

Forum home » Delegate support and help forum » Microsoft Project Training and help » project server courses - Microsoft Project

project server courses - Microsoft Project

resolvedResolved · Low Priority · Version Standard

Adrian has attended:
Project Intro Intermediate course

Microsoft Project

Is it possible to label a chain link. For example Task 1 is 'Create Building Plan' and Task 2 is 'Implement Building Plan.' The lag time would be the period in between awaiting responses. Could 'Awaiting responses from X,Y,Z' be placed next to the line linking Tasks A and B?

RE: Microsoft Project

Hi Adrian

I think your best bet would be to put the information into a note attached to the actual task.

Alternatively you could add a blank column to the table and type the information in there. There are a number of blank columns for text called text1, text 2 etc. You could insert one of those and change its heading to "Link Details" or something.

Do this by right clicking on a column head and selecting insert. A dialog will open and you can take it from there

All the best


 

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.

View all MS Project hints and tips


Server loaded in 0.1 secs.