Forum home » Delegate support and help forum » Microsoft Project Training and help » project courses london - Baseline

project courses london - Baseline

resolvedResolved · Low Priority · Version Standard

Amy has attended:
PowerPoint Introduction course
Excel Intermediate course

Baseline

What is a baseline? I don't think it's only a sporting reference....

RE: Baseline

Hi Amy!

Thanks for using the forum

Very funny!! baseline!!

A baseline is the original plan that you enter for your project. If is used to track the progress of the project!

Hope that makes sense

Tracy


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.