Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

ms project resources leveling

Forum home » Delegate support and help forum » Microsoft Project Training and help » MS Project resources, leveling

MS Project resources, leveling

ResolvedVersion 2007
Edited on Thu 2 Dec 2010, 17:27

Igors has attended:
Project Intro Intermediate course

MS Project resources, leveling

Hello!

There is one Task (fixed work) with an assigned working resource (person/persons) and some duration.
I would like to decrease duration of the Task by adding more resources, so I use additional person/persons which are finishing other tasks and becoming available (later! than start date of the Task but till the end of the Task will be available).
After that there is overallocation (new resource was busy few days from start of the Task) which was resolved by leveling.
As result we have resources with equaling hours and different start and finish dates.
But I need to have one finish date for all resources (Task must be finished by all persons).
Is there a correct way to do this? Is it possible to do this automaticaly?

Thank you!
Igor

RE: MS Project resources, leveling

Hi Igor

It sounds like leveling is doing its best to keep the resouce allocation within the max units for each resource, however to achieve this work is being carried out over a longer time frame than you'd like. Resources are alos finishing on different days.

Part of the problem may be the default behaviour of Project to start and finish tasks as early as possible.

One approach could be to try a different constraint e.g. As Late As Possible, immediately followed by a milestone with Start No Earier Than set to a date that makes sense to your project. Better yet if you create an example file showing the problem you are encountering and send it to info@stl-training.co.uk for the attention of Andrew and I will have a look at it.

Kind regards,
Andrew

RE: MS Project resources, leveling

Hi, Andrew!

Thanks,
I have e-mail files for You.

Kind regards,
Igor

MS Project tip:

Change default view – Project 2010

a. In Project, click on the File tab
b. Select General from left hand side (this should be the screen displayed by default)
c. Set the Default view dropdown box to your chosen option
d. Click OK to apply your changes

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.