msp

ResolvedVersion 2007

Nick has attended:
Project Intro Intermediate course

MSP

I have downloaded a 30 DAY demo version of MSP 2007 to use whilst in between jobs.

I am unable to open the IMG file. Any ideas on what to do?

RE: MSP

Hi Nick,

Thank you for your question.

Try Virtual Clone Drive or Magic ISO to try and open the IMG file.

I hope this helps.

Regards

Simon

RE: MSP

I tried this but it didnt work.

I have managed to download a demo of 2010 as an exe file and got that working. It s a bit different but I am finding my way around. One thing I cant find the answer to is how do you create a calender in MSP 2010?

Regards, Nick

RE: MSP

Hi Nick,

Thanks for the update.

If you go to the Project tab and then choose Change Working Time. In the top right corner there is an option to create a new calendar.

I hope this answers your question.

Regards

Simon

RE: MSP

Thanks I have created the calender and added non working days etc but how do you apply that calender for all tasks and resources in the project?

Cheers Nick

RE: MSP

Hi Nick,

Thank you for your response.

If you go to Project and Project Information and choose your new calendar from the list.

Change the calendar for the first resource in the resource sheet and use the autofill handle to fill the rest.

Then any tasks that have resources assigned to them will be using your new calendar.

Regards

Simon

Thu 9 Dec 2010: Automatically marked as resolved.

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.

View all MS Project hints and tips