lag time

Forum home » Delegate support and help forum » Microsoft Project Training and help » Lag time

Lag time

resolvedResolved · Low Priority · Version 2007

Madeline has attended:
Project Intro Intermediate course

Lag time

when is lag time used?

RE: lag time

Hello Madeline,

Hope you enjoyed your Microsoft Project Intro Intermediate course with Best STL.

Thank you for your question regarding lag and lead time.

Lag and lead time enable you to be specific about the time relationships between your tasks. You can set up gaps between linked tasks, or have them overlap.

Lag time is a delay between tasks that have a dependency. For example, if you need a two-day delay between the finish of one task and the start of another, you can establish a finish-to-start dependency and specify a two-day lag time [entered as a positive value].

Lead time is an overlap between tasks that have a dependency. For example, if a task can start when its predecessor is half-finished, you can specify a finish-to-start dependency with a lead time of 50 percent for its successor [entered as a negative lag value].

I hope this resolves your question. If it has, please mark this question as resolved.

If you require further assistance, please reply to this post. Or perhaps you have another Microsoft Office question?

Have a great day.
Regards,

Rodney
Microsoft Office Specialist Trainer

Fri 26 Nov 2010: Automatically marked as resolved.


 

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips


Server loaded in 0.08 secs.