ms project training courses london - microsoft project

Forum home » Delegate support and help forum » Microsoft Project Training and help » ms project training courses london - Microsoft Project

ms project training courses london - Microsoft Project

resolvedResolved · Low Priority · Version Standard

Elin has attended:
Project Intro Intermediate course

Microsoft Project

Does one get a discount on the advance course, once intermediate is completed?

RE: Microsoft Project

Hi Elin,

Thanks for the question, if you are a repeat customer you are entitled to


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips