Sometimes when I make changes, eg: to resources, it changes the duration of my task.

RE: Project duration

Hi Clare

Thank you for your question

Project defaults all new tasks to being "Effort Driven". This means that the more resources you add to a task, then the shorter the time that task will take to complete.

To avoid this double click on the task to open the task information dialog. Select the advanced tab and then remove the tick from the Effort Driven check box. You should also set the task type to fixed duration.

Now if the alter the number of resources, the duration will remain the same and the amount of work will alter

Regards

Stephen

Fri 18 Sep 2009: Automatically marked as resolved.

MS Project tip:

Project Community

in the help menu type "Tips" then select "Ask the Project community" this takes you into microsofts site where you can ask questions to lots of knowledgeable people.They make up an online group of experienced Project users who answer questions and provide solutions and tips.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.15 secs.