Forum home » Delegate support and help forum » Microsoft Project Training and help » Project duration

Project duration

resolvedResolved · Low Priority · Version 2007

Clare has attended:
Project Intro Intermediate course

Project duration

Sometimes when I make changes, eg: to resources, it changes the duration of my task.

RE: Project duration

Hi Clare

Thank you for your question

Project defaults all new tasks to being "Effort Driven". This means that the more resources you add to a task, then the shorter the time that task will take to complete.

To avoid this double click on the task to open the task information dialog. Select the advanced tab and then remove the tick from the Effort Driven check box. You should also set the task type to fixed duration.

Now if the alter the number of resources, the duration will remain the same and the amount of work will alter

Regards

Stephen

Fri 18 Sep 2009: Automatically marked as resolved.


 

MS Project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.

View all MS Project hints and tips


Server loaded in 0.07 secs.