Forum home » Delegate support and help forum » Microsoft Project Training and help » Splitting Task Start and Stops

Splitting Task Start and Stops

resolvedResolved · Medium Priority · Version 2003

Marci has attended:
Project Advanced course

Splitting Task Start and Stops

How to show when work on a task is paused for a period to be resumed at a later date.

RE: Splitting Task Start and Stops

Hi Marci

Thank you for your question. You may wish to create a Summary Task to describe the activity and indent the steps involved in delivering the outcome below it. You might also like to add milestones to mark the start and end of the sequence ot tasks. Now you can adjust the underlying tasks and the Summary task will calculate the overall duration.

Alternatively you may wish to create one task and use split (Edit > Split) to break the task into smaller but connected pieces.

Kind regards,
Andrew

RE: Splitting Task Start and Stops

Hi Marci,

Thank you for your question.

There are two methods to show that the remaining portion of a task needs to rescheduled for a date in the future:

1. Split the task to the desired date.
2. Use the Update Project option which is available via the Tools menu and Tracking.

I hope this answers your question.

Regards

Simon

Wed 1 Jul 2009: Automatically marked as resolved.


 

MS Project tip:

Change default view – Project 2010

a. In Project, click on the File tab
b. Select General from left hand side (this should be the screen displayed by default)
c. Set the Default view dropdown box to your chosen option
d. Click OK to apply your changes

View all MS Project hints and tips


Server loaded in 0.08 secs.