microsft office project 2003 courses in london - milestone

Forum home » Delegate support and help forum » Microsoft Project Training and help » microsft office project 2003 courses in london - Milestone

microsft office project 2003 courses in london - Milestone

resolvedResolved · Low Priority · Version Standard

Milestone

how do i create a milestone

RE: milestone

Alan

Thanks for the question

Enter a zero 0 day in the duration part of the task

Good luck

Tracy


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Server loaded in 0.06 secs.