RE: MS Project

Hi Rob

Thank you for your question. If I understand your requirement correctly one way to achieve this is to break your task down into smaller components and use milestones between each segment to represent witness points. Milestones can be updated in exactly the same way as tasks (Tools > Tracking > Update Tasks) to indicate when each point is completed.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew


 

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.

View all MS Project hints and tips


Server loaded in 0.09 secs.