project

Forum home » Delegate support and help forum » Microsoft Project Training and help » Project 2003

Project 2003

resolvedResolved · Low Priority · Version 2003

Kathryn has attended:
Project Intro Intermediate course

Project 2003

how do I sort out my lag from lack

RE: project 2003

Hi Kathryn

thank you for your question.

Lag is a delay created between two tasks. You can add delay by double clicking on the Successor task and choosing the Predecessor tab. From here you can use the lag column to add delay to the relationship.

Float describes the gap between two tasks which is created when the Successor starts later in the plan than the finish of its Predecessor. This might be because the Successor can start no earlier than a certain date or a second Predecessor is pushing it off into the future.

Lag delay is fixed. There will always be that number of days between the tasks. Float (or Slack) is flexible. That means it can be used up if the Predecessor gets delayed.

I hope this helps - do let us know if you have any further questions.


Kind regards,
Andrew

Wed 18 Mar 2009: Automatically marked as resolved.


 

MS Project tip:

Email a Task

When you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system.

1.In a task sheet, select the task or tasks which you want to send a project note.

2.On the File menu, point to Send To, and then select Mail Recipient (as Schedule Note).

3.Under Address message to, select the recipients of your note.

View all MS Project hints and tips


Server loaded in 0.07 secs.