Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

project

ResolvedVersion 2003

Kathryn has attended:
Project Intro Intermediate course

Project 2003

how do I sort out my lag from lack

RE: project 2003

Hi Kathryn

thank you for your question.

Lag is a delay created between two tasks. You can add delay by double clicking on the Successor task and choosing the Predecessor tab. From here you can use the lag column to add delay to the relationship.

Float describes the gap between two tasks which is created when the Successor starts later in the plan than the finish of its Predecessor. This might be because the Successor can start no earlier than a certain date or a second Predecessor is pushing it off into the future.

Lag delay is fixed. There will always be that number of days between the tasks. Float (or Slack) is flexible. That means it can be used up if the Predecessor gets delayed.

I hope this helps - do let us know if you have any further questions.


Kind regards,
Andrew

Wed 18 Mar 2009: Automatically marked as resolved.

MS Project tip:

Project Community

in the help menu type "Tips" then select "Ask the Project community" this takes you into microsofts site where you can ask questions to lots of knowledgeable people.They make up an online group of experienced Project users who answer questions and provide solutions and tips.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.