Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

weekends

ResolvedVersion 2003

Colin has attended:
Project Intro Intermediate course

Weekends

If a task spans a non working weekend, how do you hide the task bar over the weekend?

RE: Weekends

Hi Colin

Thank you for your question. You can format the non-working time so it sits above the bars on the Gantt chart.

From the Format menu choose Timescale then select Non-Working Time. Click the radio button to draw it in front of task bars and click OK.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

Mon 16 Feb 2009: Automatically marked as resolved.

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.