Assigning names to a task

How do I Assign more than one name to a task by percentage i.e Mary does 30% of task, Jane does 70%.

Thanks

RE: Assigning names to a task

whilst in the Gannt Chart table, click on the assign resources button from the toolbar, select the resource you wish to assign to the task and change the default "100%" to the % you wish them to be assigned to.


 

MS Project tip:

Enter a Date

You can enter today's date (or tomorrow's date) in a date field, by simply typing in the word 'today'or 'tomorrow' and Project will insert the date for you.