Project Introduction course

Andrew

When there is a taskA.1 in a projectA which is restricted by a deadline and, at the same time, there is a link between taskA.1 and taskB.1 of a projectB, how would you manage the conflict within the projects?

Thanks

RE: Andrew

Serqi

any chance of a screen shot of this?

send to forum AT stl-training.co.uk

regards

dave

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips