How do I a break link between 2 tasks? Thanks

RE: Linking tasks

Hi Ajay, the easier way, to break the link between two tasks is to double click on the line which links the two, in the Gantt chart view, then use the "Type" drop down menu and select the (None) option.

Hope this helps

Tracy

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.