Ajay has attended:
Project Intro Intermediate course
Project Introduction course
Linking tasks
How do I a break link between 2 tasks? Thanks
RE: Linking tasks
Hi Ajay, the easier way, to break the link between two tasks is to double click on the line which links the two, in the Gantt chart view, then use the "Type" drop down menu and select the (None) option.
Hope this helps
Tracy