How you enter row '0' showing project title?
RE: MS Project
Hi Manjit.
To get Row 0 or the Project Summary Task row
Click on the Gant Chart Tools - Format Tab (Top Right)
Tick the box called "Project Summary Task"
Kind regards
Richard Bailey
Microsoft Certified Trainer