resourcing

ResolvedVersion 2010

Kerry has attended:
Project Introduction course
Project Intermediate course

Resourcing

how do i export resource usage to excel so it shows a bar gragh for each resource?

Many thanks,

RE: Resourcing

Hi Kerry

Thank you for your question. You could generate the bar chart by going to the Project menu and clicking visual reports. From there take a look at the Resource work summary report. Does this provide the information you need? Let me know how you get on.
Kind regards,
Andrew

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.