How do you update progress

RE: MS Project

Hi Jacob,

Thank you for your question.

There are different ways:

1. Select the task.

2. Go the the Schedule group on the Task tab and use the buttons.

3. View the Tracking table to enter Actual information. Go to the View Tab, Data Group and choose the Tracking table from the Tables option.

If you sign into your Delegate account through www.stl-training.co.uk and provide your email address you gave in your on-line evaluation along with the four digit pass code you received at the end of that evaluation.

Select the History/Courseware tab and you can download the Project 2010 Intermediate Reference Manual(the first yellow zipped folder). This manual should outline the process in some detail.

I hope this answers your question and assists you.

Regards

Simon

Tue 19 Jul 2011: Automatically marked as resolved.

MS Project tip:

Set default task type - Project 2010

a. In Project, click on the File tab
b. Select Options from left hand side
c. Click on Schedule to set the scheduling options
d. Set the Default Task type box to your chosen option
i. Generally if you plan/estimate your projects using durations you should use fixed duration, and untick the box New tasks are effort driven, if you plan/estimate with person hours use fixed work, or for plans estimated with the proportion of resources time use fixed units, and untick the box New tasks are effort driven)
e. Click OK to apply your changes