Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

project summary

ResolvedVersion 2010

Irina has attended:
Project Introduction course

Project Summary

How do I show project summary task?

RE: Project Summary

Hello Irina,

Hope you enjoyed your Microsoft Project 2010 Introduction course with Best STL.

Thank you for your question regarding how to show the project Summary Task.

Select the Format ribbon in the Gantt Chart Tools contextual tab and from the Show/Hide group click the check box for Project Summary Task.

I presume you have already inserted the project title and other relevant information in the Advanced Properties dialogue box... if not, click the File tab and from the Info section, click the Project Information link which you will find on the right-hand side. Then select Advanced Properties and fill in the Summary tab information.

I hope this resolves your question. If it has, please mark this question as resolved.

If you require further assistance, please reply to this post. Or perhaps you have another Microsoft Office question?

Have a great day.
Regards,

Rodney
Microsoft Office Specialist Trainer

Thu 14 Jul 2011: Automatically marked as resolved.

MS Project tip:

Set default task type - Project 2010

a. In Project, click on the File tab
b. Select Options from left hand side
c. Click on Schedule to set the scheduling options
d. Set the Default Task type box to your chosen option
i. Generally if you plan/estimate your projects using durations you should use fixed duration, and untick the box New tasks are effort driven, if you plan/estimate with person hours use fixed work, or for plans estimated with the proportion of resources time use fixed units, and untick the box New tasks are effort driven)
e. Click OK to apply your changes