how do i create a milestone

RE: milestone

Kevan

Thanks for the question

Enter a zero 0 day in the duration part of the task

Good luck

Rich


 

MS Project tip:

Formatting Bar Text

To display notes or resource initials on the Gantt chart bars, choose Format, Bar Styles and the Text tab. Select the position you want to show the text i.e. Top or Inside etc, then choose the field name you are looking for from the drop down arrow. Type the first letter of the name to get quickly to the top of the letter range. Click OK.