how do I create a milestone
RE: milestone
Liam
Thanks for the question
Enter a zero 0 day in the duration part of the task
Good luck
Rich
Forum home » Delegate support and help forum » Microsoft Project Training and help » project courses london - Milestone
Liam has attended:
Project Introduction course
Project Intermediate course
how do I create a milestone
Liam
Thanks for the question
Enter a zero 0 day in the duration part of the task
Good luck
Rich
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question.
Our Microsoft Qualified trainers will then respond within 24 hours (working days).
Frequently Asked Questions
What does 'Resolved' mean?
Any suggestions, questions or comments? Please post in the Improve the forum thread.
Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.
Call for assistance
We will call you back