microsoft project course - Milestone

ResolvedVersion Standard

Tony has attended:
Project Introduction course

Milestone

how do i create the above

RE: milestone

Tony

Thanks for the question

Enter a zero 0 day in the duration part of the task

Good luck

Tracy