RE: Start dates
Hi Sandra
Thank you for your question.
If you need to change the start date of your project (before any progress has been recorded) turn on the Analysis toolbar (View > Toolbars > Analysis) and click on the Adjust dates button.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew