activity

ResolvedVersion 2003

Michael has attended:
Project Introduction course
Project Intermediate course

Activity

How do I add a sub-activity to a summary activity

RE: Activity

Hi Michael

Whenever a task is indented (the right facing arrow on the second toolbar) it becomes a sub item of the first non-indented task above it.

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew

Tue 3 Feb 2009: Automatically marked as resolved.

MS Project tip:

Keep constraining dates to a minimum

As far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields.

Date constraints such as these limit Microsoft Project's ability to automatically adjust your project whenever you add, remove or modify the duration of your tasks. Instead use the logic in your task dependencies that link your tasks to enable Project to calculate the start and finish dates for you.

View all MS Project hints and tips