How do I cater for resources that work 1/2 and full days..
where a half day is >5 and <8 hours and full day >8 hours?
RE: How do I cater for resources that work 1/2 and full days..
Hi Shrevas
Thank you for your question. If you have a mixture of resources. Some of whom work part time and others who work full time you may want to create a dedicated part-time calendar which has shorter working days (Tools > Change working time > New) and then in the resource sheet in the set the base calendar value for your part-time resources to the new calendar you created.
I hope this helps - let me know if you have any further questions.
Kind regards,
Andrew