Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

bar coding

ResolvedVersion 2003

daniel has attended:
Project Introduction course
Project Intermediate course

Bar coding

can I format colours for my scroll up bar

RE: bar coding

Hi Daniel

The individual bars that represent the rolled up tasks can be modified by double clicking on them in the chart and choosing the colour/shape. Their formatting is separate (and not linked) to the bars within the summary task

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.

View all MS Project hints and tips