Predecessors
Will insterting a new task automatically insert the predecessor?
RE: Predecessors
Hi Charlene
Thanks for your question - yes it can. You can control this option by going to the schedule tab (tools > Options > schedule) and de-selecting "autolink insterted or moved tasks"
Hope this helps - let me know if we can be of further assistance.
Kind regards,