can we set to hours and not days

RE: time

Hi Richard

Yes you can. Go to tools > options > schedule and specify the units of duration you would prefer to use.

Hope this helps - do let us know if you have any further questions.

Kind regards,

Andrew

MS Project tip:

Formatting Bar Text

To display notes or resource initials on the Gantt chart bars, choose Format, Bar Styles and the Text tab. Select the position you want to show the text i.e. Top or Inside etc, then choose the field name you are looking for from the drop down arrow. Type the first letter of the name to get quickly to the top of the letter range. Click OK.